Question
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: 1) If he
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:
1) If he uses the first come, first served (FCFS) priority rule to schedule these jobs, what will be the average completion time?
a. 7.5 hours
b. 5 hours
c. 3 hours
d. 2.5 hours
e. 2 hours
2) If he uses the earliest due date first (EDD) priority rule to schedule these jobs, what will be the average job tardiness?
a. 0 hours
b. 2.25 hours
c. 2 hours
d. 1.75 hours
e. 1.5 hours
3) If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average completion time?
a. 5 hours
b. 2 hours
c. 2.5 hours
d. 7.5 hours
e. 3 hours
4) If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average job tardiness?
a. 2.25 hours
b. 1.5 hours
c. 2 hours
d. 1.75 hours
e. 0 hoursStep by Step Solution
There are 3 Steps involved in it
Step: 1
1 A 75 Calculate FCFS as shown below T...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started