Question
The Oxford Copy Shop and Typing Pool is a local copy shop that produces course packets. Professors take copies of handout and other course-related materials
The Oxford Copy Shop and Typing Pool is a local copy shop that produces course packets. Professors take copies of handout and other course-related materials to the Copy Shop, which duplicates them and sells them to students. The jobs are due at the end of the day on the Due Dates that are provided. It is now the beginning of Day 6 and the store has the following jobs on hand:
Job | Day Brought to Shop | Processing Time (Days) | Due at the end of Day ___ |
BA 426 | 1 | 4 | 14 |
MGT 302 | 3 | 2 | 9 |
MKT 291 | 2 | 8 | 14 |
ACC 321 | 5 | 6 | 22 |
MIS 235 | 4 | 7 | 20 |
You are asked to schedule and evaluate two sequencing rules. You are ready to schedule these six jobs. They are all ready to be processed. Show all work and calculations
a) Determine the sequence of jobs using the following rules:
- Slack using the definition of the slack ratio rule that we used on our assignment
- Based on the day the job was brought to the shop
b) Prioritize the rules used in a) based on average flow time measured from now.
c) Prioritize the rules used in a) based on average lateness with no credit for completing any test early (in other words, the late time would be set at zero if a job is early).
d) Prioritize the rules used in a) based on average early time with no penalty for completing any test late (in other words, the early time would be set at zero if a job is late).
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started