The people assigned to your project have high billable rates, and the project budget doesn't provide much of a buffer over your estimated total project
The people assigned to your project have high billable rates, and the project budget doesn't provide much of a buffer over your estimated total project cost. Fortunately, the project finish date has some wiggle room. Which measure of progress is most important to track in this situation?
Select an answer:
actual start date
remaining duration
actual duration
actual work