Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The planned value for a project is US$17,800, the earned value is US$19,450, and the actual cost is US$21,870. Based on this information, calculate the

  1. The planned value for a project is US$17,800, the earned value is US$19,450, and the actual cost is US$21,870. Based on this information, calculate the cost performance index and the schedule performance index. What do these indices tell you about the status of the project in terms of cost and schedule?

2. The budget at completion of this project was estimated at US$20,000, and the original estimated time to complete was thirteen months. Use the information from the previous question to compute the estimated cost at completion and the projected time to complete. Is the project on budget and schedule?

Hint: The projected time to complete can be calculated by dividing the original estimated time to complete by the schedule performance index (SPI). (Projected time to complete = Original Estimated Time /SPI)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Entrepreneurship

Authors: Andrew Zacharakis, William D Bygrave

5th Edition

1119563097, 9781119563099

Students also viewed these General Management questions

Question

Name and explain the three types of control systems.

Answered: 1 week ago