the plant to achieve their production goals (which is based on customer demandThey are hoping to bottle 180 cases of Coca-Cola hoursIn addition, you have
the plant to achieve their production goals (which is based on customer demandThey are hoping to bottle 180 cases of Coca-Cola hoursIn addition, you have 4 stations that are part of the soda bottling process Stations to produce 1 case Station 1-4202 Seconds Molding ) 2-3902 Seconds ( ) Station 34605 Seconds Bottles with Soda ) Station 4-3588 Seconds Final Packaging StationProvide the Target Manpower for the above
I need typed answer