The post-audit of capital budgeting projects is used to
A.Revise cash flow forecasts used to improve the past analysis.
B.Allow management to revise the reports they previously completed about results and bring them into line with forecasts.
C.Eliminate potentially profitable but risky projects that were reviously adopted.
D.Improve techniques for future analyses.