Question:
The predetermined overhead rate for manufacturing overhead for 2008 is $4.00 per direct labor hour. Employees are expected to earn $5.00 per hour and the company is planning on paying its employees $100,000 during the year. However, only 75% of the employees are classified as "direct labor." What was the estimated manufacturing overhead for 2008?(Points : 1)
$60,000$75,000
$80,000
$93,750