The primary function of a change control board (CCB) in configuration management is to: Select one: a.specify the nature of changes that should be included
The primary function of a change control board (CCB) in configuration management is to:
Select one:
a.specify the nature of changes that should be included in the project
b.to initiate changes when the need for adjustment arises
c.to examine change requests principally from a technical perspective
d.to review change requests from a management perspective (e.g., impact of change on budgets, schedules, specifications)