The Problem with Priorities For the past several years, Kent Corporation had achieved remarkable success in winning R&D on tracts. The customers were pleased with
The Problem with Priorities
For the past several years, Kent Corporation had achieved remarkable success in winning R&D on tracts.
The customers were pleased with the analytical capabilities of the R&D staff at Kent Corporation.
theoretical and experimental results were usually within percent agreement. But many customers still
felt that percent was too low. They wanted percent. In Kent updated their computer facility
by purchasing a large computer. The increased performance with the new computer encouraged the R&D
group to attempt to convert from twodimensional to threedimensional solutions to their theoretical
problems. Almost everyone except the director of R&D thought that this would give better comparison
between experimental and theoretical data. Kent Corporation had tried to develop the computer program
for three dimensional solutions with their own internal R&D programs, but the cost was too great. Finally,
after a year of writing proposals, Kent Corporation convinced the federal government to sponsor the
project. The project was estimated at $ to begin January and to be completed by
December
Dan McCord was selected as project manager. Dan had worked with the EDP department on other projects
and knew the people and the manhour standards. Kent Corporation was big enough to support
simultaneous projects. With so many projects in existence at one time, continual reshuffling of resources
was necessary. The corporation directors met every Monday morning to establish project priorities.
Priorities were not enforced unless project and functional managers could not agree on the allocation and
distribution of resources. Because of the R&D directors persistence, the computer project was given a low
priority. This posed a problem for Dan McCord. The computer department manager refused to staff the
project with his best people. As a result, Dan had severe scepticism about the success of the project. In
July, two other project managers held a meeting with Dan to discuss the availability of the new computer
model. We have two proposals that were favoured to win, providing that we can state in our proposal that
we have this new computer model available for use, remarked one of the project managers. We have a
low priority and, even if we finish the job on time, Im not sure of the quality of work because of the people
we have assigned, said Dan. How do you propose we improve our position? asked a project manager.
Lets try to get in to see the director of R&D asserted Dan. And what are we going to say in our
defence? asked one of the project managers.
Project Management Case Studies Page
Harold Kerzner, PhD
QUESTION
What gave Dan McCord advantage to become the project manager? Give TWO reasons.
Although Dan had leadership advantage, Dan is not excused from being developed. Give FIVE
reasons why Dan should be developed as a project leader.
Discuss the impacts of failure to invest in developing Dan as a project leader.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started