The production manager of Rordan Corporation prepared the following quarterly production forecast for next year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to
The production manager of Rordan Corporation prepared the following quarterly production forecast for next year: 1st Quarter 2nd Quarter 3rd Quarter 4th Quarter Units to be produced 10,400 8,000 8,200 10,500 Each unit requires 0.35 direct labor-hour, and direct laborers are paid $14.00 per hour. Required: 1. Prepare a direct labor budget for next year. Note: Round "Direct labor time per unit (hours)" answers to 2 decimal places