Question

1 Approved Answer

The production schedule at Mazda calls for 1,150 Mazdas to be produced during each of 22 production days in January and 850 Mazdas to

The production schedule at Mazda calls for 1,150 Mazdas to be produced during each of 22 production days in

The production schedule at Mazda calls for 1,150 Mazdas to be produced during each of 22 production days in January and 850 Mazdas to be produced during each of 20 production days in February. Mazda uses a kanban system to communicate with Gesundheit, a nearby supplier of tires. Mazda purchases four tires per vehicle from the Gesundheit. The safety stock policy variable, a, is 0.08. The container (a delivery truck) size is 300 tires. The average waiting time plus material handling time is 1.00 day per container. Assembly lines are rebalanced at the beginning of each month. The average processing per container in January is 0.30 day. February processing time will average 0.25 day per container. How many containers should be authorized for January?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To calculate the number of containers that should be authorized for January we can use the ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations management processes and supply chain

Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra

9th edition

9788131728840, 136065767, 8131728846, 978-0136065760

More Books

Students also viewed these General Management questions

Question

What are the 5 Cs of marketing channel structure?

Answered: 1 week ago