The project budget baseline for XYZ is $3,500,000 with the following risks assessment: Risk Event Probability Impact Expected Value Parts delayed in Customs 40% $100,000
The project budget baseline for XYZ is $3,500,000 with the following risks assessment: Risk Event Probability Impact Expected Value Parts delayed in Customs 40% $100,000 Strong labor training equates to quick assembly 60% ($50,000) Heat sink assembly requires rework 85% $150,000 (source: Paul Martinsen, PMP)\
3. Calculate the adjusted project budget baseline for XYZ project.