The project duration is 40 days, and the project variance is 40.444. If the management gives your project 42 days to work on, the project
The project duration is 40 days, and the project variance is 40.444. If the management gives your project 42 days to work on, the project completion probability is________________%. This Project will require______________days to have a completion probability of 99.997% certainty for your management.