Answered step by step
Verified Expert Solution
Link Copied!

Question

00
1 Approved Answer

The Project Engineer has the following schedule plan and actual production data: Baseline Schedule Cum. Shifts Weeks per Worked Unit 5 1 1 6 3

The Project Engineer has the following schedule plan and actual production data:
Baseline Schedule Cum. Shifts Weeks per
Worked Unit
51163.2
101251.8151331.6201401.4
a. At the end of the 20th cycle (shifts worked) how many units were planned (baseline schedule) to be completed?
b. At the end of the 5th cycle, how many weeks behind is the project compared to the baseline schedule?
c. At the end of the 20th cycle, how many weeks behind is the project compared to the baseline schedule?
d. What is the observed learning rate?
e. What is the projected production rate (weeks per unit) at the 95th cycle?
f. How many weeks ahead (or behind) will the project be at the 95th cycle?
Actual Production Cum. Shifts Weeks per
Worked Unit

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these General Management questions