The project has a total budgeted amount of $200,000 and is scheduled to take 12 months. At the end of the third month the EV
- The project has a total budgeted amount of $200,000 and is scheduled to take 12 months. At the end of the third month the EV = $50,000 and a SPI of 1.1 and CPI of 1.2 and a AC of $60,000.
- What is the PV?