The project is about developing a mobile application for Transport Finder. The application allows students to find transportation using their mobile devices. It will include

The project is about developing a mobile application for Transport Finder. The application allows students to findtransportation using their mobile devices. It will include

features such as campus map, in and outside transport, andurgent orders. The project is designed to improve the transportation facilities by providing students with a user- friendly mobile application that enables them to access all the information they need. The application will be developed forboth iOS and Android platforms to ensure it is accessible to all students.

Project Goals:

1. To develop a Transport finder system that meets the needs of the students searching for any kind of transportation.
2. To ensure that the system is reliable and secure.
3. To improve communication between students and transportation staff.
4. The project should be started in the first week of November and finished within 3 months.
A. As the project manager of the given project, set the following points:
1. The working days are from Sunday to Thursday, Fridayand Saturday are the off days.
2. The working time is from 8 AM to 4 PM.
3. National days and New year are an official holiday.
4. Modify the project options based on the previous points.

B. Using MS project construct a Gantt chart by define and schedule the tasks noticing the following:
1. Set up the tasks that compose the project plan. (Dont exceed 15 tasks and 10 at minimum, the tasks should include Milestones, Summary tasks, Sub tasks, and Recurring tasks).
2. Set realistic durations for the tasks, in days or weeks ..etc. (According to the developing requirements).
3. Link the tasks appropriately. (Ensure that all tasks are linked in a logical manner from the start to the end of the project)
a) Include one Start to Start and one Start to Finish task dependency.
b) Add one lead time.
c) Add one lag time.
4. Show the critical path of the project and explain your result.
5. Outline the tasks (WBS Code).
6. Show the Gantt chart diagram:
a) The timescale of the chart must be viewed in Days.
b) The entire project chart view should be displayed in one sheet.
7. Show the Network diagram view for the project in one sheet (If possible).

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Systems In Organizations People, Technology, And Processes

Authors: Patricia Wallace

1st Edition

0136115624, 9780136115625

More Books

Students also viewed these General Management questions