The project is the construction of a shopping mall under ECC Option C and secondary Options X1, X2, X7, X18 and X20 incorporated. Any response
The project is the construction of a shopping mall under ECC Option C and secondary Options X1, X2, X7, X18 and X20 incorporated. Any response referring to dispute resolution should identify whether Option W1 or W2 applies as an assumption.
A different compensation event is assessed by the Project Manager at a much lower value than the Contractor quoted. The Contractor is concerned and 7 weeks later states that unless the assessment is revised the matter will be referred to dispute resolution? You have been asked to update the Employer.
Is the Contractor able to refer this matter to dispute resolution?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started