Question
The project management company called Sennia Projects has been approached by 1 customer for a project over the next 6 months. Project: Community Christmas party
The project management company called Sennia Projects has been approached by 1 customer
for a project over the next 6 months.
Project: Community Christmas party for 500 orphanage children in the central park:
The team will be responsible for the following:
Sourcing all equipment and materials to have a GIANT Christmas tree with Christmas carols.
Arrange transport for the 500 children to and from their orphanage.
Arranging festive eats and sweet treats for the 500 children and 250 volunteers (Includes a dinner, pudding and individually wrapped 500 small Christmas cakes for each child.
Purchase and wrapping of the 500 Christmas gifts for the children
Pay attention to the following project information:
Cost R3 500 000
Return on Investment 10%
Time to market 6 months
Risk factor Low
Chances of success High
There should be a minimum of 5 resources to manage this project. You have been given two (2)
resources, add the remaining three resources.
Resource Role Cost(per hour (8hour shift))
1. Project Manager Co-ordination of the project R300 (6 months)
2. Accounts Manager Drawing up a budget R200 (2 days)
3. Add a resource
4. Add a resource
5. Add a resource
Question 1
Making use of the information provided of the project, come up with a minimum of 40 activities that the team would need to ensure the project will be done successfully.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started