The project management team has gathered information necessary to develop a project network: predecessor activities, and activity time in days. The outcome of this meeting

The project management team has gathered information necessary to develop a project network: predecessor activities, and activity time in days. The outcome of this meeting are found in the following table:

Activity Duration Predecessor
A 5 START
B 8 A
C 3 B
D 4 A
E 5 C
F 7 C
G 6 D, E
H 8 F
I 6 G
J 5 H

Based on the provided information in the table:

1. Prepare a project network diagram

2. Indicate free float and total float for each activity

3. Calculate and identify the critical path

4. Determine the project duration

5. Prepare a Gantt chart showing the project schedule (assume a start date of Jan 1, 2019)

The assignment is divided as follows:

Sequencing of activities and network diagram (30 marks)

Float calculations (20 marks)

Identification of critical path (10 mark)

Calculation of project duration (10 mark)

Completeness of Gantt chart (30 marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals Of Project Management

Authors: James P. Lewis

3rd Edition

0814408796, 978-0814408797

More Books

Students also viewed these General Management questions