Question
The project management team has gathered information necessary to develop a project network: predecessor activities, and activity time in days. The outcome of this meeting
The project management team has gathered information necessary to develop a project network: predecessor activities, and activity time in days. The outcome of this meeting are found in the following table:
Activity | Duration | Predecessor |
A | 5 | START |
B | 8 | A |
C | 3 | B |
D | 4 | A |
E | 5 | C |
F | 7 | C |
G | 6 | D, E |
H | 8 | F |
I | 6 | G |
J | 5 | H |
Based on the provided information in the table:
1. Prepare a project network diagram
2. Indicate free float and total float for each activity
3. Calculate and identify the critical path
4. Determine the project duration
5. Prepare a Gantt chart showing the project schedule (assume a start date of Jan 1, 2019)
The assignment is divided as follows:
Sequencing of activities and network diagram (30 marks)
Float calculations (20 marks)
Identification of critical path (10 mark)
Calculation of project duration (10 mark)
Completeness of Gantt chart (30 marks)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started