Question

1 Approved Answer

The project manager for making an action movie involving a very highly paid star is very concerned about managing the project well. The following information

The project manager for making an action movie involving a very highly paid star is very concerned about managing the project well. The following information is provided.

Activity Predecessor Successor Normal Time Normal Cost Crash Time Crash Cost
A 4 $ 2000 Not available
B A 2 3000 1 $ 7000
C B 3 1000 1 2000
D B 4 2000 2 3000
E C, D 5 2000 4 6000
F E 3 1000 Not available
G E 2 4000 1 5000
H F, G 3 2000 2 4000
I H 4 1000 2 4000
J I 3 1000 2 3000

a. To shorten the project by one day, what activity should be crashed?

multiple choice

Activity A

Activity B

Activity C

Activity D

b. What is the total project cost after crashing by one day?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Sustainability and Supply Chain Management

Authors: Jay Heizer, Barry Render, Chuck Munson

12th edition

978-0134163512, 134163516, 134130421, 978-0134130422

More Books

Students also viewed these General Management questions

Question

2. What is a currency swap?

Answered: 1 week ago