The project manager for making an action movie involving a very highly paid star is very concerned about managing the project well. The following information
The project manager for making an action movie involving a very highly paid star is very concerned about managing the project well. The following information is provided.
Activity | Predecessor | Successor | Normal Time | Normal Cost | Crash Time | Crash Cost | ||
A | 4 | $ | 2000 | Not available | ||||
B | A | 2 | 3000 | 1 | $ | 7000 | ||
C | B | 3 | 1000 | 1 | 2000 | |||
D | B | 4 | 2000 | 2 | 3000 | |||
E | C, D | 5 | 2000 | 4 | 6000 | |||
F | E | 3 | 1000 | Not available | ||||
G | E | 2 | 4000 | 1 | 5000 | |||
H | F, G | 3 | 2000 | 2 | 4000 | |||
I | H | 4 | 1000 | 2 | 4000 | |||
J | I | 3 | 1000 | 2 | 3000 | |||
a. To shorten the project by one day, what activity should be crashed?
multiple choice
Activity A
Activity B
Activity C
Activity D
b. What is the total project cost after crashing by one day?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started