The project manager has completed the project management plan and sent it to the sponsor, other key stakeholders, and team leads for their approval. Upon
The project manager has completed the project management plan and sent it to the sponsor, other key stakeholders, and team leads for their approval.
Upon review, one of the team leads notices an important activity is missing and requests that it be added to the project management plan. What should th
project manager do
A Submit a change request because the team lead has already performed the impact analysis and stated that the activity needs to be added.
B Perform an impact analysis of the missing activity.
Add the missing activity to the project management plan.
Advise the team lead that adding the activity at this stage is gold plating.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started