The project manager has updated the sponsor with a project report that lists the SPI as being 1.2 and the CPI as .6. The sponsor
The project manager has updated the sponsor with a project report that lists the SPI as being 1.2 and the CPI as .6. The sponsor is very upset and would like the PM to correct this action as soon as possible. What should the project manager do next