Question

1 Approved Answer

The project manager is facing a rush project and the PMO office has authorized the project team to work 7.0 days per week (work week

The project manager is facing a rush project and the PMO office has authorized the project team to work 7.0 days per week (work week for this project). The PM would like to provide the PMO office with a project duration estimate based on a 75% probability of completion on time. The project has an estimated duration of 67 work days, which was based on estimates including an optimistic estimate of 36 and a pessimistic estimate of 82. The PM has looked up 75% on her probability table for a normal distribution and Z is equal to 0.67. How many work weeks should the PM tell the steering committee the project will take?

Step by Step Solution

3.39 Rating (143 Votes )

There are 3 Steps involved in it

Step: 1

To estimate the project duration based on a 75 probability of completion on time we can use the ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Modern Systems Analysis And Design

Authors: Joseph Valacich, Joey George

8th Edition

0134204921, 978-0134204925

More Books

Students also viewed these Accounting questions

Question

List five properties of relations.

Answered: 1 week ago