The project manager is reviewing the Cost Performance Report. She notices that the 50/50 Rule was applied to a work activity that is 40 work

The project manager is reviewing the Cost Performance Report. She notices that the 50/50 Rule was applied to a work activity that is 40 work days in duration. What should the project manager do?

Group of answer choices

A. Have the Earned Value recalculated using the 0/100 Rule since the activity is 40 workdays in length.

B. Have the Earned Value recalculated using the Milestone Weights method since the activity is greater than 20 workdays in length.

C. Have the Earned Value recalculated using the Percent Complete method since the activity is 40 days or less in length.

D. Nothing. The rule is accurately applied.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Finance And Accounting Essential Theory And Practice

Authors: Rob Van Ginneken

1st Edition

0429015119, 9780429015113

More Books

Students also viewed these General Management questions

Question

Why was the phi phenomenon so important to Wertheimer?

Answered: 1 week ago