Question

1 Approved Answer

The project original budget at completion is 100,000 WH. The total earned value is 90,000 WH with a cumulative CPI of 0.95. The project

 

The project original budget at completion is 100,000 WH. The total earned value is 90,000 WH with a cumulative CPI of 0.95. The project has expended a total of 94,737 WH. (The project duration is within seven percent of completion.) You are the project manager. Which one of following ETCS would you report to senior managers?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project management the managerial process

Authors: Eric W Larson, Clifford F. Gray

5th edition

73403342, 978-0073403342

More Books

Students also viewed these Civil Engineering questions

Question

How does a communication plan benefit management of projects?

Answered: 1 week ago

Question

Why do firms outsource project work?

Answered: 1 week ago

Question

=+a. Draw a diagram of this RAID system.

Answered: 1 week ago

Question

=+b. Calculate the reliability at t 5 800,000 cycles.

Answered: 1 week ago