Question
1 Approved Answer
The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the
The project risk manager on a large firm fixed priced (FFP) contract has an up-to-date risk register with accurate and detailed information. What should the project risk manager do next? Quantify the risk exposure that exceeds project contingency Recommend the removal of risks to the project manager to reduce project risk exposure. Advise the client that the project has exhausted contingency. Generate reports to assess and communicate the project risk level