The project sponsor is very concerned that the project completes on time and has directed the project manager to use the most talented personnel in
The project sponsor is very concerned that the project completes on time and has directed the project manager to use the most talented personnel in the organization in order to ensure the project finishes on schedule. What risk strategy best describes this scenario