The project sponsor seeks to ensure that the due date for specific functionality is included. When Project Chartering using Agile methods, where do you define
The project sponsor seeks to ensure that the due date for specific functionality is included. When Project Chartering using Agile methods, where do you define when will it be done?
a Milestone schedule.
b Progressive elaboration.
c Releases and iterations.
d Authorize, understand, commit, screen.