The project team deployed a weighed scoring model as a systematic selection process to select the best project that support the desired deliverables. Study the

The project team deployed a weighed scoring model as a systematic selection process to select the best project that support the desired deliverables. Study the different criteria and their assigned weights in the table below. Note the numerical scores for each Project that has been assigned to each criteria. Calculate the weighted score for Project 1.
\table[[Criteria,Weight,Project 1 Project 2,Project 3 Project 4,,],[Supports key business objectives,28%,85,90,70,75],[Has strong internal sponsor,14%,70,85,75,80],[Has strong customer support,10%,80,85,65,60],[Uses realistic level of technology,5%,95,95,95,95],[Can be implemented in one year or less,15%,25,30,25,20],[Provides positive NPV,18%,70,75,85,80],[Has low risk in meeting scope, time, and cost,10%,30,40,65,35],[goals,,,,,63,85]]
a.65.4
b.66.7
c.65
d.66
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

SQL Instant Reference

Authors: Gruber, Martin Gruber

2nd Edition

0782125395, 9780782125399

More Books

Students also viewed these Databases questions

Question

How could Lewins force field analysis be applied to this project?

Answered: 1 week ago

Question

describe how work-time control can promote recovery.

Answered: 1 week ago

Question

=+How is CSR different from strategic CSR?

Answered: 1 week ago