The project team is building a fence and they want to allow 2 days for the cement posts to dry before installing the fence. This
The project team is building a fence and they want to allow 2 days for the cement posts to dry before installing the fence. This is an example of? Select the best answer. Question 10 options: Crashing the project Levelling the project A lag A lead Increasing the project scope