The project team is currently working on a project to upgrade all the servers across the organization. Before they were able to get the financial
The project team is currently working on a project to upgrade all the servers across the organization. Before they were able to get the financial server, the vendor call and said the server delivery has been delayed by 2 weeks. What documents should the project manager update immediately