The purchasing agent of the Charlton Company ordered materials of lower quality in an effort to economize on price. Due to a mistake in production

The purchasing agent of the Charlton Company ordered materials of lower quality in an effort to economize on price. Due to a mistake in production scheduling by the production manager, the materials were rush-shipped by airfreight at a rate higher than that ordinarily charged for shipment by truck, resulting in an unfavorable materials price variance. The lower quality material proved to be unsuitable on the production line and resulted in excessive waste. In this situation, who should be held responsible for the materials price and quantity variances? Explain.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

First lets understand what materials price variance and quantity variance mean 1 Materials Price Variance This is the difference between the standard ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting

Authors: James Jiambalvo

4th edition

9780470546888, 9780470333341, 470546883, 470333340, 978-0470578797

More Books

Students also viewed these Accounting questions

Question

What is a job cost sheet? What information does it contain?

Answered: 1 week ago