The recommended approach for managing a software development project with unstable requirements would be _ _ _ _ . Group of answer choices waterfall Joint
The recommended approach for managing a software development project with unstable requirements would be
Group of answer choices
waterfall
Joint Application Development JAD
Rapid Application Development RAD
agilescrum
Step by Step Solution
There are 3 Steps involved in it
Step: 1