Question
The Risk Gantt Chart displays risk critical tasks which are: 1.Tasks originally on the critical path, but can be combined with other risk critical tasks,
The Risk Gantt Chart displays risk critical tasks which are:
1.Tasks originally on the critical path, but can be combined with other risk critical tasks, resulting in slack time for each of the tasks.
2 Tasks not originally on the critical path, but during the simulation they could not be completed prior to the estimated project completion date.
3.Tasks which are 100% certain to finish later than their most likely completion date.
4.Tasks not originally on the critical path, but during the simulation they appear on the critical path more than a user-specified percentage of time
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started