Question
The risk response of acceptance is typically be used for: a. risks which are simply not manageable by any means b. risks that are too
The risk response of "acceptance" is typically be used for:
a. risks which are simply not manageable by any means
b. risks that are too trivial to warrant management
c. risks that a project sponsor and stakeholders publicly agree to take
d. any or all of the above
According to conclusions reached by our textbook author when studying the PERIL database, black swans appeared to cause the most impact in terms of which risk category?
a. cost or budget risk
b. scope risk
c. schedule risk
d. quality risk
In general, how does the planning horizon impact project risk?
a. the longer the project, the higher the risk, because you may not be able to see what's ahead
b. the longer the project, the lower the risk, because you have more time to recover if necessary
c. the longer the project, the lower the risk because the team learns from mistakes as time goes on
d. none of the above
In terms of schedule risk, analysis of the PERIL database indicates a large number of project schedule delays due to:
a. insufficient budgeting
b. lack of team member training
c. inadequate project facilities
d. poor activity duration estimates
One method often used to settle on a task duration from a set of estimates that seem to be widely spaced apart is:
Select one:
a. critical path analysis
b. PERT formula
c. root cause analysis
d. fishbone diagram
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started