The Rolling Department of Oak Ridge Steel Company had 4,300 tons in beginning work in process inventory (40% complete) on July 1. During July, 71,500
The Rolling Department of Oak Ridge Steel Company had 4,300 tons in beginning work in process inventory (40% complete) on July 1. During July, 71,500 tons were completed. The ending work in process inventory on July 31 was 3,600 tons (70% complete). What are the total equivalent units for direct materials for July if materials are added at the beginning of the process