The schedule below was developed for a construction project. A contract was entered into to deliver the project within 12 days. A clause in the

The schedule below was developed for a construction project. A contract was entered into to deliver the project within 12 days. A clause in the contract stated that the project contractor will be penalised R5,000 per day for each day that the project was delayed and R1,000 per day should the project be successfully concluded earlier than the 12 stipulated days. Answer the questions that follow and be sure to adhere to all technical requirements for diagrams and calculations required.


1. Create an activity on node (AON) network diagram for the schedule above.

2. Find the critical path using slack for the schedule above.

ACTIVITY A B C D E LU F G H 1 K L M N 0 DURATION (Days) 1 3 1 2 3 2 3 2 5 SO 2 PREDECESSOR A D D C B H G EJ F J L KM

Step by Step Solution

3.34 Rating (145 Votes )

There are 3 Steps involved in it

Step: 1

activity duration predecessor ES EF LS LF slack A 1 0 1 0 1 0 B 3 0 3 3 6 3 C 1 0 1 1 2 1 D 2 A 1 3 ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations management processes and supply chain

Authors: Lee J Krajewski, Larry P Ritzman, Manoj K Malhotra

9th edition

9788131728840, 136065767, 8131728846, 978-0136065760

More Books

Students also viewed these Computer Network questions