The schedule variance for a project is calculated by: Select one: a. EV-PV b. PV-EV c. CU-EV d. EV-AC Which of the following is not

The schedule variance for a project is calculated by:

 

Select one:

a. EV-PV

b. PV-EV

c. CU-EV

d. EV-AC

 

Which of the following is not an example of communications noise?

 

Select one:

a. A document written in black ink when it was meant to be written in blue ink

b. A document file that was corrupted when it was sent via email

c. A speech that was given in French to an audience that only speaks English

d. Speaking in a low voice in a large room

 

Which of the following is most expected to be contained in the risk register?

 

Select one:

a. The risk responses

b. A list of the people with the assigned task of planning the risk responses

c. The cost of the human resources assigned to respond to the risk

d. A list of the stakeholders that may be affected by the risks

 

 

Step by Step Solution

3.38 Rating (157 Votes )

There are 3 Steps involved in it

Step: 1

1 A EV PV Schedule variance can be represented as the difference between the ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting concepts and applications

Authors: Albrecht Stice, Stice Swain

11th Edition

978-0538750196, 538745487, 538750197, 978-0538745482

More Books

Students also viewed these Accounting questions