Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The Seneca Company (Civil Engineers) consists of two divisions. The divisions are Transportation and Infrastructure. The company sells engineering services to various customers. The following

The Seneca Company (Civil Engineers) consists of two divisions. The divisions are Transportation and Infrastructure. The company sells engineering services to various customers. The following are the bill rates for the various staff classifications:

Vice President

$250/hour

Senior Engineer

$200/hour

Associate Engineer

$190/hour

Staff Engineer

$160/hour

The two divisions expect to bill the following hours:

Transportation - 10,000 hours, vice president at 10% of the time, 20% of Senior Engineer time 10% to Associate engineers and remaining to Staff Engineers.

Infrastructure - 6,000 hours, vice president at 12% of the time, 20% of Senior Engineer time, 5% to Associate engineers and remaining to Staff Engineers.

The Direct Labor costs per hours are as follows:

Vice President

$90/hour

Senior Engineer

$70/hour

Associate Engineer

$60/hour

Staff Engineer

$50/hour

The utilization (billable ratio to total hours) for each staff member is as follows:

Vice President

60%

Senior Engineer

80%

Associate Engineer

85%

Staff Engineer

90%

The company has the following other costs:

Admin Salaries

$81,000

Rent

$120,000

Utilities

$16,000

Benefits

$75,000

Assume that there are 2080 hours per year that each engineer can work including vacation and other benefit hours.

You are an outside third party Human Resources consulting firm and the Seneca Company Board of Directors, CFO and the CPO have engaged your company. The goal of the Board, CFO and the CPO is to improve profitability of the divisions and company. Therefore, to accomplish providing engagement advice to the Board, CFO and CPO the consulting team should answer the following questions during the presentation and in the final report.

1.Prepare a static budget for the company.

2.Assume that the actual utilization came in at the following rates:

Vice President

50%

Senior Engineer

82%

Associate Engineer

88%

Staff Engineer

93%

3.Based on the above utilization, prepare a flexible budget and calculate the Level 2/3 variances.

4.What recommendations can be made for the upcoming year in budgeting to the CFO for additional profitability and increasing revenue?

5.What approaches would your recommendations to increase the company overall utilization of staff and billable hours?

6.How will your recommendations impact customer profitability or divisional profitability?

7.The company wants to add a new division. It will be the Construction Division with 3 people. Please discuss pros and cons of adding a division and when you might consider not adding the division.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Principles Managerial Concepts

Authors: Jerry J. Weygandt, Donald E. Kieso, Paul D. Kimmel, Barbara Trenholm, Valerie Kinnear, Joan E. Barlow

7th Canadian Edition

1119310296, 978-1119310297

More Books

Students also viewed these Accounting questions

Question

What is the work environment like? Friendly/collegial?

Answered: 1 week ago

Question

1. Maintain my own perspective and my opinions

Answered: 1 week ago