The Shapely Company uses the high-low method to determine its cost equation. The following information was gathered for the past year: Machine Hours Direct Labor
The Shapely Company uses the high-low method to determine its cost equation. The following information was gathered for the past year: |
Machine Hours | Direct Labor costs | |||
Busiest month(June) | 14,750 | $ | 770,000 | |
Slowest month (December) | 9,750 | $ | 620,000 |
If Shapely expects to use 12,000 machine hours next month, what are the estimated direct labor costs? |
$687,500.
$1,008,260.
$510,000.
$400,969.