The Shapely Company uses the high-low method to determine its cost equation. The following information was gathered for the past year: Machine Hours Direct Labor

The Shapely Company uses the high-low method to determine its cost equation. The following information was gathered for the past year:

Machine Hours Direct Labor costs
Busiest month(June) 14,750 $ 770,000
Slowest month (December) 9,750 $ 620,000

If Shapely expects to use 12,000 machine hours next month, what are the estimated direct labor costs?

$687,500.

$1,008,260.

$510,000.

$400,969.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing Principles Practice And Problems

Authors: Jagdish Prakash

1st Edition

9327244745, 978-9327244748

More Books

Students also viewed these Accounting questions