Question
The Simpson Construction Company recognizes revenue over time based on the percentage of completion of its long-term construction contracts. In 2016, Simpson began working on
The Simpson Construction Company recognizes revenue over time based on the percentage of completion of its long-term construction contracts. In 2016, Simpson began working on a construction contract. The information on this contract at the end of 2016 is as follows:
Cost incurred during the year | $1,500,000 |
Estimated additional cost to complete | 6,000,000 |
Gross profit recognized in 2016 | 250.000 |
What is the contract price (total revenue) in this contract?
Step by Step Solution
3.51 Rating (164 Votes )
There are 3 Steps involved in it
Step: 1
Progress complete x contract pric...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Financial Reporting And Analysis
Authors: Lawrence Revsine, Daniel Collins, Bruce Johnson, Fred Mittelstaedt, Leonard Soffer
8th Edition
1260247848, 978-1260247848
Students also viewed these Accounting questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App