The sponsor of your project has asked for the schedule performance index. You have calculated the Earned Value at $5,342. The planned value at this
The sponsor of your project has asked for the schedule performance index. You have calculated the Earned Value at $5,342. The planned value at this time is $6,200. Which of the following best describes the answer you will provide to your sponsor? the spi i .86 and we are behind schedule or the spi .86 and we are ahead of schedule