The St . Lucia Blood Bank, a private charity partly supported by government grants, is located on the Caribbean island of St . Lucia. The

The St. Lucia Blood Bank, a private charity partly supported by government grants, is located on the Caribbean island of St. Lucia. The blood bank has just finished its operations for September, which was a particularly busy month due to a powerful hurricane that hit neighbouring islands, causing many injuries. The hurricane largely bypassed St. Lucia, but the residents of St. Lucia willingly donated their blood to help people on other islands. As a consequence, the blood bank collected and processed 24% more blood than had been originally planned for the month.
A report prepared by a government official comparing actual costs to budgeted costs for the blood bank appears below. (The currency on St. Lucia is the East Caribbean dollar.) Continued support from the government depends on the blood bank's ability to demonstrate control over its costs.
The managing director of the blood bank was very unhappy with this report, claiming that her costs were higher than expected due to the emergency on the neighbouring islands. she also pointed out that the additional costs had been fully covered by payments from grateful recipients on the other islands. The government official who prepared the report countered that all of the figures had been submitted by the blood bank to the government; he was just pointing out that actual costs were a lot higher than promised in the budget.
Required:
Prepare a new performance report for September using the flexible budget approach. (Note: Even though some of these costs might be classified as direct costs rather than overhead, the flexible budget approach can still be used to prepare a flexible budget performance report.).(Indicate the effect of each variance by selecting "F" for favourable, "U" for unfavourable, and "None" for no effect (i.e., zero variance). Round "Cost Formula" answers to 2 decimal places)The St. Lucia Blood Bank, a private charity partly supported by government grants, is located on the Caribbean island of St. Lucia. The blood bank has just finished its operations for September, which was a particularly busy month due to a powerful hurricane that hit neighbouring islands, causing many injuries. The hurricane largely bypassed St. Lucia, but the residents of St. Lucia willingly donated their blood to help people on other islands. As a consequence, the blood bank collected and processed 24% more blood than had been originally planned for the month.
A report prepared by a government official comparing actual costs to budgeted costs for the blood bank appears below. (The currency on St. Lucia is the East Caribbean dollar.) Continued support from the government depends on the blood banks ability to demonstrate control over its costs.
ST. LUCIA BLOOD BANK
Cost Control Report
For the Month Ended September 30
Actual Budget Variance
Litres of blood collected 1,080600480 F
Variable costs:
Medical supplies $ 8,900 $ 9,000-$100 F
Lab tests 12,2308,100 $4,130 U
Refreshments for donors 2,6501,2001,450 U
Administrative supplies 600300300 U
Total variable cost 24,38018,6005,780 U
Fixed costs:
Staff salaries 19,50019,500
Equipment depreciation 4,8003,5001,300 U
Rent 1,9501,950
Utilities 770600170 U
Total fixed cost 27,02025,5501,470 U
Total cost $ 51,400 $ 44,150 $ 7,250 U
The managing director of the blood bank was very unhappy with this report, claiming that her costs were higher than expected due to the emergency on the neighbouring islands. she also pointed out that the additional costs had been fully covered by payments from grateful recipients on the other islands. The government official who prepared the report countered that all of the figures had been submitted by the blood bank to the government; he was just pointing out that actual costs were a lot higher than promised in the budget.
Required:
1. Prepare a new performance report for September using the flexible budget approach. (Note: Even though some of these costs might be classified as direct costs rather than overhead, the flexible budget approach can still be used to prepare a flexible budget performance report.).(Indicate the effect of each variance by selecting "F" for favourable, "U" for unfavourable, and "None" for no effect (i.e., zero variance). Round "Cost Formula" answers to 2 decimal places)
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: John Hoggett, Lew Edwards, John Medlin, Keryn Chalmers, Jodie Maxfield, Andreas Hellmann, Claire Beattie

9th Edition

1118608208, 978-1118608203

More Books

Students also viewed these Accounting questions

Question

How well is Kering performing relative to LVMH?

Answered: 1 week ago

Question

Compare and contrast cultural preferences for online privacy

Answered: 1 week ago

Question

Provide examples of the various microcultures in the United States

Answered: 1 week ago