Question
The standard cost of making a single product is: 10kg @$2.00 per kg 20.00 5 hours @$5.00 per hour 25.00 5hours @3.00 per hour 15.00
The standard cost of making a single product is:
10kg @$2.00 per kg 20.00
5 hours @$5.00 per hour 25.00
5hours @3.00 per hour 15.00
$60.00
The factory overhead rate is based on a budgeted production of 10,000 units for the year, and
budgeted fixed factory overhead of $50,000.
Actual transactions and results for the year were:
Direct Materials purchased 95,000kgs @ 2.05 per kg
Direct Materials used 92,000 kgs
Direct labour incurred 46,000 hours @ 4.90 per hour
Factory Overhead incurred $140,000
Number of units produced 9,000
Calculate:
(i) two variances for Direct material (3 marks)
(ii) two Variances for direct tabour (2 marks)
(iii) two variances each for fixed and variable overheads (6 marks)
Show all working out in determining the variances
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started