The standard cost of product 2525 includes 4.70 hours of direct labour at $13.15 per hour. The predetermined overhead rate is $21.30 per direct labour
The standard cost of product 2525 includes 4.70 hours of direct labour at $13.15 per hour. The predetermined overhead rate is $21.30 per direct labour hour. During July, the company incurred 11,480 hours of direct labour at an average rate of $13.45 per hour and $237,264 of manufacturing overhead costs. It produced 2,400 units.
(a)
Calculate the total, price, and quantity variances for labour.
Total labour variance | $enter a dollar amount | select a type of the variance |
---|
Labour price variance | $enter a dollar amount | select a type of the variance |
---|
Labour quantity variance | $enter a dollar amount | select a type of the variance |
---|
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started