The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of actual production are as follows: Standard Costs Fixed overhead
The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of actual production are as follows:
Standard Costs
Fixed overhead (based on 10,000 hours)3 hours per unit @ $0.72 per hourVariable overhead3 hours per unit @ $2.01 per hour
Actual Costs
Total variable cost, $18,100Total fixed cost, $8,100
The amount of the total factory overhead cost variance is
a.$3,187 favorable
b.$3,187 unfavorable
c.$1,819 unfavorable
d.$4,555 favorable
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started