The standard costs and actual costs for factory overhead for the manufacture of 2,500units of actual production are as follows: Standard Costs Line Item Description

The standard costs and actual costs for factory overhead for the manufacture of 2,500units of actual production are as follows:

Standard Costs
Line Item Description Value
Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.71 per hour
Variable overhead 3 hours per unit at $1.95 per hour

Actual Costs Total variable cost, $18,000 Total fixed cost, $7,800

The total factory overhead cost variance is

a.$5,150 favorable

b.$5,150 unfavorable

c.$6,925 favorable

d.$3,375 unfavorable

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing And Assurance Services An Integrated Approach

Authors: Alvin A. Arens, Randal J. Elder, Mark S. Beasley, Chris E. Hogan

18th Edition

0137879199, 9780137879199

More Books

Students also viewed these Accounting questions

Question

Sketch a radial drilling machine and explain its working.

Answered: 1 week ago

Question

=+ (b) Show that X ,, - p X.

Answered: 1 week ago