The standard direct labor cost per unit for a company was $24 (= $16 per hour 1.5 hours per unit). During the period, actual direct
The standard direct labor cost per unit for a company was $24 (= $16 per hour 1.5 hours per unit). During the period, actual direct labor costs amounted to $154,900, 9,900 labor-hours were worked, and 5,300 units were produced.
Required: Compute the direct labor price and efficiency variances for the period. (Indicate the effect of each variance by selecting "F" for favorable, or "U" for unfavorable. If there is no effect, do not select either option.)
Price Variance:
Efficency Variance:
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started