Question

1 Approved Answer

The standard factory overhead rate is $12 per machine hour ($10 for variable factory overhead and $2 for fixed factory overhead) based on 100% capacity

The standard factory overhead rate is $12 per machine hour ($10 for variable factory overhead and $2 for fixed factory overhead) based on 100% capacity of 42,000 machine hours. The standard cost and the actual cost of factory overhead for the production of 2,000 units were as follows:

Actual: Variable factory overhead$350,500Fixed factory overhead84,000Standard: 35,000 hours @ $12420,000

Determine the (a) volume variance, (b) controllable variance, and (c) total factory overhead cost variance.

a.Volume variance$fill in the blank 1

b.Controllable variance$fill in the blank 2

c.Total factory overhead cost variance$fill in the blank 3

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Advanced Financial Accounting An IFRS Standards Approach

Authors: Pearl Tan, Chu Yeong Lim, Ee Wen Kuah

4th Edition

9789814821278, 9814821276

More Books

Students also viewed these Accounting questions

Question

What are some of the benefits of being a critical thinker? (p. 231)

Answered: 1 week ago